N/A Sungrow — Inverter Replacement Commissioning
At a glance
- Severity
- WARNING
- Domain
- INVERTER_FV
- Reference standard
- CEI 0-21 / CEI 0-16 / Regola Tecnica di Connessione del Distributore
- Product / context
- iSolarCloud Commissioning Wizard
What it means
Commissioning procedure after replacing a PV inverter. Includes configuration of CEI 0-21 protection parameters, grid code setting, verification of correct operation, and notification to the distribution operator.
Probable causes
- Inverter replacement due to irreparable fault (power board, lightning damage).
- Inverter upgrade to a newer model or different size.
- Preventive replacement under warranty for a known manufacturer defect (recall/service bulletin).
- Regulatory update requiring inverter replacement for CEI 0-21 ed. 2019 compliance.
- Replacement of the associated datalogger or SmartLogger.
Where to start
Before installing the new inverter, verify compatibility: does the maximum DC voltage of the strings fall within the inverter range? Is the string short-circuit current below the MPPT input Isc max? Is the new inverter the same size (or compatible) as the previous one?
Full guided diagnosis in the app
The diagnostic tree for this fault has 11 guided steps with measurements, checks and resolutions. You'll find it in ElectraIQ, one of the four IndexOS apps: free, works offline.